要理解线束IE工艺工程师的工作内容及方法,首先需要清楚线束生产的过程,本文线束工程师之家网将带你熟悉线束IE的具体工作内容。
线束供应商生产某个车型线束产品的必要过程:文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►主机厂发出报价需求文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►供应商报价文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►主机厂发送定点告知文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►手工样件阶段文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►工装样件阶段文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►小批量阶段文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►批量生产批准文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►批量生产文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
每个阶段IE工作解析如下:文章源自线束工程师之家-https://www.suncve.com/work-contents-and-methods-of-harness-process-engineer/
►在报价阶段根据项目信息和报价图纸输出标准工时、布局图、面积需求、人员需求、投资报价表(工装、设备、刀模、其他)、设备购置计划、产品加工特殊特性、过程失效模式分析、生产制造可行性分析;
►在手工样件阶段输出人员配置、样件区域布局图、开线工艺;
►在批量生产前进行持续改进以及维护客户的工程更改。
►在工装样件阶段之前搭建生产系统,具体工作如下:
1) 根据最新项目信息和正式量产图纸更新标准工时、布局图、面积需求、人员需求、投资报价表(工装、设备、刀模、其他)、设备购置计划、产品加工特殊特性、过程失效模式分析、生产制造可行性分析;
2) 制作工程计划;
3) 定义导线长度,输出开线工艺,前序操作指导书,目视文件;
4) 按照生产节拍进行后序作业初分;
5) 根据初分工艺实测每个工位的实际工时,根据实测工时适当调整工作量,最后输出工位平衡图以及每个工位的操作指导书;
6) 设计分装板及流水线主板图并组织其他部门评审案板图签字留档;
7) 根据操作指导书设计每个分装工位精益管架子图,分析流水线案板操作人员密度,定义流水线案板数量;
8) 计算及输出辅助工具及特殊工具种类及数量;
9) 制作卡钉模块、电测台模块等特殊防错和辅助操作模块技术确认,包含数量需求;
10) 制作卡钉、电测、视觉等测试设备导入基础数据;
11) 建立地址系统,制作出料工艺,制作各类标识及卡片,输出出料路径图;
12) MBOM录入并核对录入结果;
13) 输出爬坡计划并跟踪爬坡结果;
14) 培训生产员工。